01 NCAC 30D .0304 DESIGNER OR CONSULTANT SELECTION FOR UNC SYSTEM PROJECTS
In selecting designers or consultants for its projects, the UNC system shall comply with the preceding policies and pre‑selection procedures, except that pre‑selection committees need not include a representative of the State Construction Office. The UNC system shall establish its own procedures for final designer or consultant selection. These procedures shall correspond in form to those established below for other than UNC system projects and shall be filed with and approved by the SBC.
History Note: Authority G.S. 143‑135.25; 143‑135.26;
Eff. January 1, 1988;
Amended Eff. May 1, 1990;
Pursuant to G.S. 150B-21.3A, rule is necessary without substantive public interest Eff. July 22, 2018.